Difference between revisions of "PT Calendar2 Configuration"
From ADF Docs
Gcronkright (talk | contribs) (Created page with 'Back to Build Subsites, Templates and Pages') |
|||
(One intermediate revision by one other user not shown) | |||
Line 1: | Line 1: | ||
Back to [[PT Calendar2 Build Subsites Templates and Pages|Build Subsites, Templates and Pages]] | Back to [[PT Calendar2 Build Subsites Templates and Pages|Build Subsites, Templates and Pages]] | ||
+ | |||
+ | == Overview == | ||
+ | The Calendar Configuration Page will be used to manage the PTCalendar Configuration custom element. Follow these steps to configure the datasheet and page for adding calendar configuration. | ||
+ | |||
+ | == Steps == | ||
+ | # Create a new page called 'Configuration Manager' in the ''/webadmin/calendar/'' subsite. | ||
+ | # In the main content of the page, add a Custom Script element. | ||
+ | # Enter the explicit module path for: | ||
+ | ## ''/ADF/apps/pt_calendar2/customcf/manage_configuration_header.cfm'' | ||
+ | # From the Datasheet element interface, click the "Datasheet" icon. | ||
+ | # From the "Datasheet Views" dialog, follow the "Click here to create a new datasheet view" link. | ||
+ | # Enter the following information and then click "Next": | ||
+ | ## Name: Calendar Configuration | ||
+ | ## Private: unchecked | ||
+ | ## Default View: checked | ||
+ | ## Description: View to manage the Calendar Configuration | ||
+ | ## Datasheet Source: Form Result/Custom Element Sheet | ||
+ | # From the Datasheet Source dialog choose the "ptCalender2 Configuration" custom element and click "Next". | ||
+ | # From the Datasheet Columns Dialog choose a few columns from the Available Columns list and move them to the Selected Columns list. (CS_USERS_DSN, Calendar_App_UI_Theme, Calendar_App_ToolTip_Theme, etc...) and then click "Finish". | ||
+ | # You will be brought to the Datasheet View page; click "Close" to return to your page. | ||
+ | # You will see the datasheet element on this page now. Click the Datasheet element interface icon again and this time choose "Edit Columns". | ||
+ | # From the Datasheet View Column Properties dialog choose the link for "Add a new action column". | ||
+ | # Within the Action Column Properties dialog enter the following information and click "Finish": | ||
+ | ## Header: Edit | ||
+ | ## Hide Header: Checked | ||
+ | ## Column Text: edit | ||
+ | ## Window Target Name: <leave blank> | ||
+ | ## Modules: edit-form-data.cfm | ||
+ | # Close the Edit Column window. | ||
+ | # Publish the page. | ||
+ | |||
+ | == Create Calendar Configuration Record == | ||
+ | <!-- | ||
+ | '''Note''' that this step assumes that you have [[PT_Calendar2_Calendar_Template|Calendar Template]] previously created the admin pages]]. --> | ||
+ | |||
+ | We are creating a single Calendar Configuration element record to be used within the application. | ||
+ | |||
+ | Go to the Add Configuration page and submit the form to create '''one record'''. | ||
+ | |||
+ | These fields will be completed as the pages are built. | ||
+ | |||
+ | See the [[PT Calendar2 Site Configuration|Site Configuration]] wiki page for more information on the fields and the correct values. | ||
+ | |||
+ | [[Reset ADF|Reset the ADF]] for the server and site. | ||
+ | |||
+ | [[Category:Calendar]] |
Latest revision as of 20:18, 2 March 2011
Back to Build Subsites, Templates and Pages
Overview
The Calendar Configuration Page will be used to manage the PTCalendar Configuration custom element. Follow these steps to configure the datasheet and page for adding calendar configuration.
Steps
- Create a new page called 'Configuration Manager' in the /webadmin/calendar/ subsite.
- In the main content of the page, add a Custom Script element.
- Enter the explicit module path for:
- /ADF/apps/pt_calendar2/customcf/manage_configuration_header.cfm
- From the Datasheet element interface, click the "Datasheet" icon.
- From the "Datasheet Views" dialog, follow the "Click here to create a new datasheet view" link.
- Enter the following information and then click "Next":
- Name: Calendar Configuration
- Private: unchecked
- Default View: checked
- Description: View to manage the Calendar Configuration
- Datasheet Source: Form Result/Custom Element Sheet
- From the Datasheet Source dialog choose the "ptCalender2 Configuration" custom element and click "Next".
- From the Datasheet Columns Dialog choose a few columns from the Available Columns list and move them to the Selected Columns list. (CS_USERS_DSN, Calendar_App_UI_Theme, Calendar_App_ToolTip_Theme, etc...) and then click "Finish".
- You will be brought to the Datasheet View page; click "Close" to return to your page.
- You will see the datasheet element on this page now. Click the Datasheet element interface icon again and this time choose "Edit Columns".
- From the Datasheet View Column Properties dialog choose the link for "Add a new action column".
- Within the Action Column Properties dialog enter the following information and click "Finish":
- Header: Edit
- Hide Header: Checked
- Column Text: edit
- Window Target Name: <leave blank>
- Modules: edit-form-data.cfm
- Close the Edit Column window.
- Publish the page.
Create Calendar Configuration Record
We are creating a single Calendar Configuration element record to be used within the application.
Go to the Add Configuration page and submit the form to create one record.
These fields will be completed as the pages are built.
See the Site Configuration wiki page for more information on the fields and the correct values.
Reset the ADF for the server and site.